FERTILIZER PLANT
MARY TURKMENISTAN
Location: Mary, Turkmenistan
Client: Renaissance Heavy Industries
Contract Type: Construction- Contractor
Start Date: October 2011
Date of Completion: December 2013
Construction Period: 26 months
Project Status: Completed
Scope of Works:
- Piping Erection and Prefabrication Works (155.000 wdi)
- Structural Steel Erection Works (4.200 ton)
- Cladding Works (Sandwich and Trapeze) (7.500 m²)
- Equipment Erection Works (650 ton) such as,
Air Cooled Heat Exchangers Erection Works
Bagging Building Equipment Works
Conveyor System Erection Works
Overhead Crane Erection Works