Location: Svobodny, Russia
Client : Renaissance Heavy Industries
Contract Type : Construction – Contractor
Start Date : September 2018
Date of Completion : December 2021
Contsruction Period : 40 months
Project Status : Completed

Piping Erection and Prefabrication Works (700.000 wdi)
Structural Steel Erection Works (13.000 ton)
Cladding Works (50.000 m2)
Steam Tracing Works (125.000 m)
Flare Erection Works (650 ton)