RUSVINYL IKRA PROJECT INTEGRATED VINYLS PLANT

NIZHNY NOVGOROD RUSSIA

Location: Nizhny Novgorod, Russia
Client : Renaissance Heavy Industries
Contract Type : Construction – Contractor
Start Date : May 2012
Date of Completion : March 2014
Contsruction Period : 22 months
Project Status : Completed

Piping Erection and Prefabrication Works (100.000 wdi)
Structural Steel Erection Works (3.000 ton)
Cladding Works (7.000 m2)
Equipment Erection Works (330 ton)
Insulation Works (30.000 m2)