SIBUR ZAPSIB-2 ETHYLENE CRACKER UNIT PLANT

TOBOLSK RUSSIA

Location: Tobolsk, Russia
Client: Renaissance Heavy Industries
Contract Type: Construction- Contractor
Start Date: August 2016
Date of Completion: September 2019
Construction Period: 38 months
Project Status: Completed
Scope of Works:

  • Piping Erection and Prefabrication Works (620.000 wdi)
  • Furnace Erection Works (3ea x 1.900 ton, 5.700 ton)